O07 Site

Site overview

The O07 site is located at the corner of West Carson Street and Chartiers Avenue in McKees Rocks Borough. It will serve as the starting point for the Chartiers Creek Branch Tunnel, which will run underground and connect to the main Ohio River Tunnel at the O27 site. The tunnel will capture combined sewage from the Chartiers Creek drainage area before it reaches the river.

Construction at O07 will include a large vertical shaft approximately 50 feet wide and 150 feet deep, as well as modifications to the existing river outfall.

Once construction is complete, the area will be restored as close to its current condition as possible. Restoration will include security fencing and new landscaping designed to enhance the appearance of the property and complement the surrounding business center.

Site preparations, including the demolition of existing buildings, were completed in early 2026.

Chartiers Avenue & West Carson Street, McKees Rocks Directions: Google Maps Apple Maps

Beneath the surface

Go beyond the construction fence and explore the O07 site.

Underground Cross Section

Cross-section illustration of the Ohio River Tunnel facilities underneath the O07 site located near the former Crivelli Building in the McKees Rocks Plaza in McKees Rocks Borough. The image shows an access shaft that connects to the Chartiers Creek Tunnel located about 150 feet below ground surface. The access shaft is approximately 50 feet in diameter. The image also shows n outfall modification, three manholes, and a tunnel vent location. Surface buildings, streets, trees, and subsurface soil and bedrock layers are displayed to illustrate the local context.

Aerial Site Plan

Aerial site plan showing the location of the Ohio River Tunnel (ORT) facilities underneath the O07 site located near West Carson Street in McKees Rocks Borough. An access shaft connects to the Chartiers Creek Tunnel. The plan also identifies a tunnel vent, outfall sewer, and modified outfall. Shaded areas indicate the limits of construction and locations of intermittent road closures, with local streets, buildings and parking lots providing context for the construction site location. The plan notes that the former Crivelli building will be used and maintained during construction.

What to expect during construction

Nearby businesses and residents may experience some construction impacts during the project, including intermittent noise during shaft excavation and increased traffic entering and exiting the site via West Carson Street.

To help minimize impacts to the surrounding business community and residents, ALCOSAN will:

  • Keep public parking available outside active construction areas.
  • Install fencing around active construction areas to help protect public safety.
  • Implement dust-control and traffic-management measures throughout construction.

ALCOSAN is committed to working with the surrounding community to minimize disruption and will provide updates to help residents and businesses understand what to expect during each phase of the project.

Permitted work hours at this site will be:

General work hours*

  • 7:00 a.m. to 7:00 p.m. Monday through Friday

*Impact-producing construction activities, such as pile driving and jackhammering, are limited to 8:00 a.m. to 6:00 p.m., Monday through Friday. Controlled blasting activities are limited to 7:00 a.m. to 7:00 p.m., Monday through Friday. Work hours exclude legal holidays; limited exceptions, including emergencies, may apply.

What's happening at O07

Closures, public meetings and construction updates for the O07 site.